Elara Engineering has successfully completed a comprehensive MEPFP infrastructure replacement project – spanning three phases over three consecutive summers – that addressed aged and inefficient equipment for the all-electric Dundee Middle School building. Prior to project completion, the building had been served by 50-year-old, direct expansion cooling and electric heating, variable air volume handlers, and package roof top units.
Specific building infrastructure upgrades include:
- New geothermal heating and cooling system
- Packaged DOAS equipment
- New lighting
- New fire alarm system
- New emergency generator
- New domestic water system


Geothermal Heating and Cooling
At the start of the project, a detailed energy model was completed including geothermal modeling to design a 90 bore vertical geothermal well field routed to an existing, stand-alone pump house that was converted to accept the geothermal piping wells and manifold, including associated primary pumps that serve the building’s air-cooled VRF condensers. Under Elara’s design, geothermal water serves indoor water cooled variable refrigerant condensers and horizontal concealed VRF evaporators with the ability to simultaneously heat or cool individual spaces.
Ventilation
Dundee Middle School’s ventilation is now provided by packaged, direct expansion cooling, natural gas heating DOAS equipment ducted to each space. Ventilation air is controlled by VAV boxes to regulate outside air based on CO2 readings to not over-ventilate the space and to reduce ventilation when spaces are unoccupied.
Construction Phasing
Each summer’s construction phase ensured that each area completed was successfully served by the geothermal system while the original portion of the building remained in service until scheduled for renovation.
Additional information about this project can be found here.