Elara’s Energy Audit and HVAC/Mechanical Systems Assessment Report identified
opportunities to reduce operating costs with potential estimated savings up to
$241,100 per year
• Identified incentive funding from local utilities for energy efficient commercial
HVAC and lighting projects
• Designed and replaced three air-cooled chillers with two cooling-only chillers and one
heat recovery chiller to achieve a projected $116,000 in annual utility cost savings
• Designed solutions to minimize flood impacts on life safety, hotel functionality,
and building damage